Case Study: Arthur Erikson Place
Arthur Erikson Place
Hybrid Domestic Hot Water Case Study

Project Summary
Arthur Erikson Place is an iconic 26-story office building co-owned by KingSett Capital, Crestpoint Real Estate Investments Ltd. (in joint venture with Vestcor Inc.), and Reliance Properties Ltd., located in downtown Vancouver.
Prior to the project to retrofits its domestic hot water (DHW) system, hot water in the building was generated by different gas-fired boilers depending on the season. In the heating season, two large 3,077 MW (10,500 MBtu/hr) gas-fired boilers, dating from the original construction, were used for DHW production and also provided hot water for hydronic space heating. These large boilers were turned off during the cooling season and three smaller gas-fired boilers, ranging from 88 MW (300 MBtu/hr) to 147 MW (500 MBtu/hr), were used instead. One of these three smaller boilers provided DHW for the tower while the other two were dedicated to the fitness centre change rooms. The DHW was stored in two large 1,325 L (350 US gallon) storage tanks, both original to the building.
The copper risers, running vertically through two mechanical shafts beside the elevator shaft, were also original to the building and had begun to leak on occasion. This signaled to Colliers that the risers were approaching the end of their long service life and required replacement.
Each year, Kingsett Capital, one of the building owners, holds an Innovation in Sustainability competition for projects at their managed properties. For the 2020 competition, Kingsett indicated that they were particularly interested in seeing submissions focused on technologies that were cutting-edge, had not yet scaled up to mass adoption, or were new to the Canadian or North American market. The award prize was a $50,000 contribution towards the winning project.
For its submission to the competition, Colliers proposed to combine the planned replacement of the aging risers with the electrification of the tower’s DHW system to significantly reduce the building’s GHG emissions. The electrification project would include decoupling the large boilers from the DHW systems, replacing the boiler serving the tower with two sets of all-electric, CO2-based heat pumps for year-round DHW generation, and installing new DHW storage tanks. Electrification of the DHW system for the change rooms was not part of the proposal because the two boilers for this system were less than ten years old.
The project won the internal competition and was approved for some additional funding from the CleanBC Better Buildings program, and Colliers was tasked with implementing it.
Annual Savings:
- 640 GJ
- 32 GHG (TONNES C02e)
- 15 Payback (years)
Project Outcomes
The new system was commissioned in 2021 and has been operating successfully to provide the building with DHW without issue. Since implementation, this project has reduced the building’s energy consumption by an average of 640 GJ annually, and reduced its GHG emissions by approximately 32 tCO2e/year (at full occupancy). In addition to reducing the building’s operational emissions, the CO2 refrigerant used in the system also reduced the emissions-impact of a potential refrigerant leak.
Assuming full occupancy, an increase in electrical consumption of approximately 60 MWh/yr, and a carbon tax escalation of $170/tCO2e by 2030, Colliers estimates the payback period of the retrofit to be 15 years. The project cost $146 per tonne of CO2e savings considering the incentives received but not factoring in any anticipated reductions in maintenance costs.
Based on an average run time and indoor installation (protected from precipitation and high humidity), the heat pumps are expected to have a service life of 15 to 20 years with annual or semi-annual maintenance. After the expected service lifespan, it may be possible to simply replace worn-out components rather than replacing the entire heat pump.
Colliers has recently begun to monitor the energy consumption of the new domestic hot water systems with dedicated submeters. In addition to providing specific energy consumption data for the DHW systems, the submetering should provide a means of detecting operational issues as they occur. This will allow Colliers to maintain and repair the systems in a timely manner and should maximize the service life of the heat pumps.
Based on the success of this project, Colliers and the project team are now working with the building owners to design and implement a net-zero carbon retrofit plan to electrify all of the building’s remaining gas equipment by 2025.
The original DHW system was assessed by the project team to ensure proper sizing of the new equipment. Concerned that simply following American Society of Plumbing Engineers (ASPE) guidelines could lead to oversizing of equipment, the designer refined the sizing calculations with a third party-reviewed, manual calculation which took into account the building’s low-flow fixtures and time-of-day usage patterns for certain fixtures. This ensured that the replacement equipment would be appropriately sized for the specific hot water heating demands of the building.
Since the tower’s DHW system is divided into two loops – one serving the upper 16 floors of the building and one serving the floors below – two separate right-sizing exercises had to be undertaken. The designer determined that six heat pumps and four 450 L (119 US gallon) storage tanks would be required for the upper system, and four heat pumps and three 450 L storage tanks would be required for the lower system. Because the original boilers were retained to continue providing space heating for the building, the new all-electric DHW heating plants required new homes. Non-tenanted spaces on the top floor and parkade level were converted to secondary mechanical rooms to accommodate the new equipment.
An important consideration for many electrification projects is the electrical service to the building, in particular the difference between the peak demand and the maximum capacity. In this case, the typical peak demand was approximately 1,500 kW, representing less than 40% of the available service. The project team determined that there was more than enough spare capacity for the DHW electrification project, which would add no more than 100 kW to the building’s electrical demand. The panelboards to which the heat pumps would connect also had spare capacity and therefore did not have to be replaced.
As is often the case in older office towers, there was enough room in the mechanical chase to install a new riser while the adjacent existing riser was in use. This allowed the contractor to install the new equipment in the new secondary mechanical rooms and connect it to the new riser without disrupting the water supply to the building. Once the new system was tested and commissioned, it was tied into the existing branch piping outside of regular office hours because this part of the work involved shutting off the water supply to the building or several floors at a time. The switchover was completed at the end of April 2021.
Because CO2-based heat pump water heaters require low supply water temperatures to maximize efficiency, the temperature of the hot water recirculation loops is maintained using one electric swing tank for each system instead of the heat pumps. The swing tanks, installed in the secondary mechanical rooms, are equipped with electric resistance coils to keep the temperature in the recirculation loop at 55℃ (131℉).
According to the contractor, a big advantage of the model of heat pump water heaters chosen for the project is that, because the CO2 refrigerant they use is sealed entirely within the heat pump units, they can be installed by plumbers rather than requiring specialized refrigeration technicians. This reduced the installation cost of the system compared to systems where refrigerant lines are installed in the building.